BOSCO CONSTRUCTORS, INC.
Project 9906
Project:
|
9906
|
Name:
|
Winter Park Wastewater Treatment Plant
|
Location:
|
Winter Park, Colorado
|
Owner:
|
Winter Park Water & Sanitation District |
|
Winter Park, Colorado 80482
|
Architect/Engineer:
|
URS Greiner Woodward Clyde
|
|
4582 South Ulster street, Suite 1000
|
|
Denver, Colorado 80237
|
|
303-740-3928
|
Contract Amount:
|
$1,398,272
|
Percent
Complete: |
85% |
Scheduled
Completion: |
February 2000 |
Project
Scope: |
Phase 2 wastewater treatment plant expansion
- Partially buried concrete aeration basin, aeration basin pump
gallery, aeration basin CMU superstructure, process equipment,
process piping, electric and control systems, mechanical systems,
sitework.
|
|