BOSCO CONSTRUCTORS, INC.
Projects Completed in the Past Five Years Pump Stations
Back to Project List
PUMP STATIONS
Project: |
9715 |
Name: |
Back Flow Preventor |
Location: |
Littleton, Colorado |
Owner: |
Lockheed Martin Astronautics |
Architect/Engineer: |
LockheedMartin Astronautics |
Contract Amount: |
$603,526 |
Completion: |
September 1997 |
Project Scope:
Construction of the new pumphouse facility and
remove existing structors. The work includes site preparation, earthwork,
and backfill, asphalt paving, fencing, seeding, and landscape, erosion
control, cast-in-place concrete, structural steel framing, metal roofing,
doors and hardware, finish painting, plumbing system, HVAC, fire protection,
electrical and control systems.
Project: |
9714 |
Name: |
INVERNESS PUMP
STATION |
Location: |
Englewood, Colorado |
Owner: |
Inverness Water and
Sanitaion District |
|
2 Inverness Drive
East, Suite 600 |
|
Englewood, Colroado
80112 |
Architect/Engineer: |
Meurer & Associates |
|
143 Union Blvd.,
Suite 600 |
|
Lakewood, Colorado |
Contract Amount: |
$207,434.00 |
Completion: |
July 1997 |
Project Scope:
Installation of additional pumps in two existing
pump stations, including associated piping, electrical controls and a new
emergency generator.
Project: 9712
Name: WOODMAN VALLEY PUMPING STATION
Location: |
Colorado Springs,
Colorado |
Owner: |
Colorado Springs
Utilities |
|
30 South Nevada |
|
Colorado Springs,
Colorado 80947 |
Architect/Engineer: |
URS Greiner, Inc. |
|
1040 South 8th
Street, Suite 100 |
|
Colorado Springs, Colorado
80906 |
|
719-634-6699 |
Contract Amount: |
$365,499.00 |
Completion: |
August 1997 |
Project Scope:
Install cast-in-place concrete pump station including
yard pipe, tie-ins, interior pipe, high service pumps and electrical controls.
Project: |
9711 |
Name: |
88TH
STREET WATERMAIN |
Location: |
Louisville, Colorado |
Owner: |
Storagetek |
|
Louisvill, Colorado |
Architect/Engineer: |
Martin/Martin |
Contract Amount: |
$634,475 |
Completion: |
October 1997 |
Project Scope:
Installation os approximately 4000 LF of 12" watermain
metering and backpressure sustaining vaults; construct a precast booster
pump station with variable speed pump skid and associated piping; demolition
of existing pump station and water tank, dirtwork and grading, raodbase
and paving.
Project: |
9704 |
Name: |
VALLEY PUMP STATION
IMPROVEMENTS |
Location: |
Ken-Caryl Ranch,
Colorado |
Owner: |
Ken Caryl Ranch Water
& Sanitation District |
|
10698 Centennial
Road |
|
Littleton, Colorado
80127 |
Architect/Engineer: |
Black & Veatch |
|
11900 East Cornell
Ave., Suite 300 |
|
Aurora, Colorado
80014 |
|
Mr. Lance Lindeman |
|
303/671-4296 |
Contract Amount: |
$247,495 |
Completion: |
July, 1997 |
Project Scope:
This project consisted of the installation of 2
new horizontal split case pumps into an existing system including: new
piping, valving, electrical and controls.
PROJECT: |
9618 |
NAME: |
NORTHGLENN PUMP
STATION |
LOCATION: |
Northglenn, Colorado |
Owner: |
City of Northglenn |
|
11701 Community Center
Drive |
|
Northglenn, Colorado
80233-1099 |
Architect/Engineer: |
HDR Engineering,
Inc. |
|
303 East 17th
Ave., Suite 300 |
|
Denver, Colorado
80203 |
|
303/861-1300 |
Contract Amount: |
$239,949 |
Completion: |
June, 1997 |
Project Scope:
The modification to the existing booster pump station
including two new variable frequency drives, one jockey, a 350 KW diesel
generator and a programmable RTU. The modification to the city water treatment
plant included pipe, controls, and valving changes to the plant influent
flow control system.
Project: |
9520 |
Name: |
HOGBACK PUMP STATION |
Location: |
Littleton, Colorado |
Owner: |
The Southwest Metro
Water & San. District |
|
8739 West Coal Mine
Ave. |
|
Littleton, Colorado
80123 |
Architect/Engineer: |
Meurer & Associates |
|
143 Union Blvd.,
Ste. 600 |
|
Lakewood, Colorado
80228 |
|
Mr. Keith Bushdiecker |
|
303/985-3636 |
Contract Amount: |
$575,091 |
Completion: |
June, 1996 |
Project Scope:
Construction of a pump station with associated
piping, equipment installation, sitework, etc. for a complete pump station.
Project: |
9518 |
Name: |
GREENWOOD PLAZA
PUMP STATION |
Location: |
Greenwood Village,
Colorado |
Owner: |
Greenwood Plaza Water
District |
|
% R.S. Wells Corporation |
|
6200 South Syracuse
Way |
|
Greenwood Village,
Colorado 80111 |
Architect/Engineer: |
KLH-TriConsultants |
|
605 Parfet Street,
Suite 200 |
|
Lakewood, Colorado
80215 |
|
303/235-0266 |
|
Mr. Jack Moody |
Contract Amount: |
$69,208 |
Completion: |
May, 1996 |
Project Scope:
Install water booster system and 300 GPM bypass
pump and piping. Perform earthwork, erosion control, and concrete trickle.
Project: |
9516 |
Name: |
LOUISVILLE/SUPERIOR
PUMP STATION |
Location: |
Louisville, Colorado |
Owner: |
Northern Colorado
Water Conservancy District |
|
1250 North Wilson
Avenue |
|
Loveland, Colorado
80539 |
Architect/Engineer: |
Black & Veatch |
|
11900 E. Cornell,
Suite 300 |
|
Aurora, Colorado
80014 |
|
303/671-4200 |
|
Mr. Dave Vidikan |
Contract Amount: |
$863,675 |
Completion: |
April, 1996 |
Project Scope:
Construct .5 MGD in-line booster pump station with
horizontal centrifugal pumps driven by adjustable-frequency drives. Construct
masonry structure with cast-in-place concrete foundation and floor slab.
Install pumping units, electrical gear, piping, equipment, instrumentation,
lighting, HVAC and plumbing.
Project: |
9510 |
Name: |
WATER TRANSFER
PUMP STATION |
Location: |
Lafayette, Colorado |
Owner: |
City of Lafayette |
|
1290 South Public
Road |
|
Lafayette, Colorado
80026 |
Architect/Engineer: |
McLaughlin Water
Engineers, Ltd |
|
2420 Alcott Street |
|
Denver, Colorado
80211 |
Contract Amount: |
$64,818 |
Completion Date: |
August 1995 |
Work with Own
Forces: |
60% (Concrete work,
piping, equipment installation) |
Project Scope:
Construct concrete pump vault, an 8" DIP pipeline
and connect to existing pipeline for 2 MG per day facility.
Project: |
9509 |
Name: |
GUN CLUB ROAD
PUMPING STATION |
Location: |
Aurora, Colorado |
Owner: |
City of Aurora |
|
1470 South Havana
Street |
|
Aurora, Colorado
80012 |
|
Ms. Brenda Agner,
C.P.M. |
Architect/Engineer: |
Black & Veatch |
|
Aurora, Colorado |
|
Mr. Dave Vidikan |
|
303/671-4200 |
Contract Amount: |
$1,193,225 |
Completion Date: |
March 1995 |
Project Scope:
Construct combination 15 MGD potable water pumping
station and 1 MGD rainwater pumping station, yard pipe, motors, electrical
chemical feed system HVAC equipment, and generator.
Project: |
9509 |
Name: |
SANITARY SEWAGE
LIFT STATION IMPROVEMENTS |
Location: |
Englewood, Colorado |
Owner: |
Waste Management
of Colorado, Inc. |
|
Englewood, Colorado
80921 |
Architect/Engineer: |
Meurer and Associates,
Inc. |
|
143 Union Boulevard,
Suite 600 |
|
Lakewood, Colorado
80228 |
|
(303) 985-3636 |
|
Mr. Greg Sekera |
Contract Amount: |
$40,270 |
Completion Date: |
May, 1995 |
Work with Own
Forces: |
60% (Concrete work,
piping, equipment installation) |
Project Scope:
Remove and replace concrete slab, install sanitary
sewage pumping equipment and new pump control panel.
Project: |
9501 |
Name: |
BOOSTER STATION
NO. 3 IMPROVEMENTS |
Location: |
Colorado Springs,
Colorado |
Owner: |
Gleneagle Water District |
|
15850 Holbein Drive |
|
Colorado Springs,
Colorado 80921 |
|
(719) 488-3603 |
Architect/Engineer: |
GMS, Inc. |
|
611 N. Weber, Suite
300 |
|
Colorado Springs,
Colorado 80903 |
|
(719) 475-2935 |
|
Mr. Roger Sams |
Contract Amount: |
$127,717 |
Completion Date: |
May, 1995 |
Work with Own
Forces: |
60% (Concrete work,
piping, equipment installation) |
Project Scope:
Install two canned vertical turbine pumps and one
multistage pump complete with new piping, electrical and control equipment
for new pumps.
Project: |
9313 |
Name: |
SOUTH BOOSTER
PUMP STATION |
Location: |
Monument, Colorado |
Owner: |
Woodmoor Water &
Sanitation District |
|
P.O. Box 1407 |
|
Monument, Colorado
80132 |
|
(719) 488-2525 |
|
Mr. Phil Steininger |
Architect/Engineer: |
Rothberg, Tamburini
& Winsor, Inc. |
|
19 N. Tejon St.,
# 202 |
|
Colorado Springs,
Colorado 80903 |
|
(719) 520-5999 |
|
Mr. Paul Gilbert |
Contract Amount: |
$156,541 |
Completion Date: |
June, 1994 |
Work with Own
Forces: |
60% (Concrete work,
piping, equipment installation) |
Project Scope:
Construct booster pump station building as an addition
to existing building. Install piping, pumps, electrical, controls, heating
and ventilating equipment and modify existing pump station electrical system
and controls.
Project: |
9302 |
Name: |
SLOAN LAKE IRRIGATION
PUMP INSTALLATION |
|
AND PUMP ROOM
MODIFICATIONS |
Location: |
Denver, Colorado |
Owner: |
City and County of
Denver |
|
303 West Colfax Ave.,
Suite 675 |
|
Denver, Colorado
80204 |
|
(303) 640-2382 |
|
Mr. Randy Anderson |
Architect/Engineer: |
City and County of
Denver |
|
Parks & Recreation |
|
2300 15th
Street, # 150 |
|
Denver, Colorado
80202 |
|
(303) 964-2543 |
|
Mr. Rod Wiberg |
Contract Amount: |
$250,858 |
Completion Date: |
May, 1993 |
Work with Own
Forces: |
60% (Concrete work,
equipment installation) |
Project Scope:
Remove and salvage portions of existing pump station.
Furnish and install a 30" C.M.P. pipe and new prefabricated pump station
for irrigation system.
Back to Project List
|